Research — Auto Demo · Precomputed (draft, unvalidated)
Duct bank: one feeder becomes four — auto
No controls here: six short stories play on their own. A bank grows from one conduit to four and its ampacity falls below the first feeder. Wider spacing changes the trench but not the number. Deeper burial makes it worse; a lower soil resistivity or separate banks fix it. Then concrete sizing and a crowded conduit. Use Pause, or the story and step buttons, to stop on any frame.
Story
Duct bank · end view of the trench, bank and conduits
Bank ampacity vs feeder loads
Ampacity by bank shape · same cable, soil, burial and ambient
Every check at this step · the controlling row is highlighted
Rule column: the citation the data file gives for each check. None of these limits is checked against a published standard here.
How the checks read it
Every check · the problem, the change, the fix
Required values are the functions' own defaults for these cables, read from the data file: the fill limits and the grouping source have no checked citation. A row marked value is a number the function returns with no verdict. The feeder row is the exporter's own comparison against invented loads.
design_duct_bank_layout, calculate_conduit_fill, calculate_duct_bank_ampacity, calculate_trench_dimensions, calculate_concrete_encasement.Not modeled: heat flow between conduits or between banks, spacing as an input to ampacity (the function has none), encasement as an input to ampacity, a thermal-backfill model (a lower soil resistivity number is the only stand-in), cooler ground at depth, per-conduit ampacity (one number covers the whole bank), cable pulling, vault sizing, and any standards-based limit. The conduit trade size is used as the drawn diameter, the conduit wall is drawn at a fixed width so it can be seen, and the street, soil and trench art are a fixed illustrative backdrop.See also:Duct bank, interactive with free play · Cable pull, vault to vault · Conduit fill